BidCraft Tile
BidCraftTile
Jump to…

Lines on your bids

Some work is always inside your tile price. Some trades you never touch. Lines on your bids tells BidCraft both, so new bids come out the way you'd write them.

Open Settings → Bid settings → Your proposal and tap Lines on your bids.

What's in your prices?

Check the work that's already inside your tile price: thinset, grout, caulk, waterproofing, backer board, edge trim, floor prep.

On a new bid, checked work never gets a line of its own. It goes inside the tile line, and the line says so ("includes grout and caulking"). This works whether your bids are one line per room or itemized.

Other trades and fees

Each trade shows your answer under its name. Tap a trade to change it:

  • Always. Every new bid gets one line for it, from your job type's template or your price list. From your price list, only something you charge as a flat price, per item or by the day is added, one of it. If you have neither, nothing is added.

  • Sometimes. BidCraft adds it only when the job calls for it. This is how every trade starts.

  • I sub it out. You hire someone else for it. New bids price that line at the sub's quote plus your markup on subs, never your own labor price. See Work you sub out.

  • Never. New bids leave it off.

Dumpster and permits are fees, so they have Always, Sometimes and Never.

Questions BidCraft has stopped asking

On a new job, BidCraft asks a few quick checks before it drafts: are permits required, is the shower getting a niche, is it getting a bench. Say no to the same one job after job and it stops asking:

  • Permits stops after a no on two jobs in a row.
  • A shower niche and a shower bench each stop after a no on three jobs in a row.

A check you leave unanswered when you draft counts as a no. A yes keeps the question going. If Permits above is set to Never, the permits check is not asked at all.

Once a question has stopped, a new job is drafted with your usual no, the same as if you had tapped it. The question shows at the bottom of this panel under Questions I've stopped asking. Tap Ask again to bring it back. Until something has stopped, that section isn't there.

When a job's notes mention a permit, a niche or a bench, the line is still drafted. Permits set to Never above works as before: new bids leave permits off.

What your client sees

When your proposal shows exclusions, trades you set to Never are listed at the end of the line items as Not included: Plumbing, Permits. If you add a line for one of them to the proposal, it comes off that list.

Changing one bid

Your answers shape new bids. You can still change any bid:

  • Add a line for a trade you set to Never, and it stays on that bid, even when you rebuild the proposal.
  • Delete a line BidCraft added because of Always, and it stays off that bid.
  • Delete a line and add it back, and BidCraft stops leaving it out.

Bids you've already sent don't change unless you rebuild them.

How you list your work

When you take a line BidCraft drafted off a bid, BidCraft learns how you list that work, in the same words the bid shows:

  • Inside “Shower wall tile” (or Inside the room's main line). New bids name that work inside the other line instead of giving it its own.
  • Only when a job asks. New bids add it only when your notes or measurements call for it.
  • Only when your notes ask. New bids leave it off unless your notes ask for it.

A line that came from your template or your starting list of lines is different: taking it off changes nothing on your account. Under Left off this bid, that line shows Just this job already picked, with the other choice beside it. Tap the other choice only if you want new bids to list that work the same way every time; those lines follow it from then on. Tap Just this job again to take it back.

Lines your pricing rules add (a trip charge, for example) never offer this choice, and neither do lines BidCraft adds because you answered Always. A line for plumbing, electrical, glass, demo, fixtures, paint and drywall, a dumpster or permits doesn't offer it either, but only when you answered that one above with Always, Never or I sub it out: your answer decides it. If you left it unanswered or picked Sometimes, the line offers the choice like any other. If you answer it after a line was taken off an older bid, that line still shows the choice. Tapping it then tells you the work follows your answer here, and from then on the line shows only its name and Add back.

Once BidCraft has learned something, this list appears at the bottom of the panel. Each line shows the job and the date it came from. If that work's service is no longer in your catalog, the line says so.

Changed your mind? Tap Draft it again, then Save. New bids draft that line as before, and the next time you take it off, BidCraft starts fresh.

If you never take lines off your bids, you won't see this list.

More than one kind of client

If you have a proposal style for each kind of client (homeowners and builders, for example), pick the client at the top of the panel. Each one keeps its own answers.

Was this article helpful?
Still need help?

Email andy@businessupai.com and a real person on the BidCraft Tile team will get back to you. If you're signed in, you can also ask Biddy from any page in the app.